The construction of the Oxford's new wastewater treatment plant by Dewberry & Davis, Inc. is progressing on schedule and on budget. The walls of the new oxidation ditch now tower over surrounding tools and equipment.
Workers continue excavating, laying pipe, and backfilling for the
new 18-inch tertiary drain line from the influent pump station and
for the new 18-inch RAS force main to the oxidation ditch.
Pouring concrete for the 38th wall of the oxidation ditch.