Construction Progress Report -
July 2006 - Expected completion August 2006


Bypass lines at the headworks

Still on schedule and on budget, Dewberry & Davis, Inc. is finishing structures and setting equipment for Oxford's new wastewater treatment plant. The new bypass line at the headworks protects Fishing Creek by carrying any overflows to the clarifier.


Control panel and motor for aerators

Workers have installed the motor and control panels for the
aerator at the oxidation ditch.


Building the dumpster pad at the headworks

The forms are in place for a pad to support the new compactor and dumpster for removing trash and paper from the water that flows into the headworks.